A sealed IGU is a component system—glass, coating, spacer, desiccant, primary and secondary seals, gas and glazing conditions must work together over time.

A unit develops haze between the panes. The supplier points to an IG certification label; the buyer assumes the label guarantees this individual unit for the building’s lifetime. Neither conclusion is sufficient. Certification can provide evidence for a defined product family and controlled process, while the field condition still requires unit identity, observation, manufacturing and installation evidence.

Technical and warranty boundary: Only competent investigators and the applicable certification, contract and warranty processes can determine conformity, cause and remedy. This guide does not diagnose an individual IGU from photographs.

1. Review the IGU as a complete assembly

FGIA describes insulating glass as a combination of panes, spacer, desiccant, sealants, gas fill, coatings and optional internal grids. Changing one element may affect compatibility, certification coverage, fabrication controls or durability.

Record the exact assembly used for the project—not only ‘double glazed’. Include each lite and coating surface, cavity, spacer, desiccant route, primary/secondary seal, gas specification, internal components and fabricator.

IGU configuration identity
ComponentProject record
Glass litesThickness, substrate, heat treatment/lamination
CoatingsProduct and numbered surface
CavityWidth and gas specification
Spacer/desiccantSystem and colour/type
Seal systemPrimary and secondary sealants
Internal elementsGrid/blind/decorative components
Fabricator/modelPlant, product family and traceability

2. Verify what certification actually covers

FGIA’s public IG certification explanation identifies ASTM E2188, E2189 and E2190 among qualification routes and describes witnessed samples, recorded components, independent testing, product-family authorisation, plant surveillance and periodic retesting. Check the current directory, fabricator, plant, model and label—not a generic certificate image.

Certification is evidence of conformity to its program requirements for the listed assembly; it is not a promise that every field unit will remain clear forever or that every substitution is covered. Record the program, listing status, assembly description, issue/validation period and project match.

Certification applicability check
QuestionEvidence
Which program/standard?Current named program and edition/criteria
Who and where fabricated?Listed company and plant
Which product family?Directory/model and assembly components
Is the label valid?Permanent unit mark and current listing
Does project make-up match?Component-by-component comparison
What remains outside scope?Installation, damage, warranty and service conditions

3. Describe the visible condition before naming it

Clean and inspect both accessible faces safely. Record whether haze, droplets, deposits, fingerprints, scratches or coating effects appear on an exposed surface or within the cavity. Use consistent lighting, angle and photographs; reflections can make a surface condition appear internal.

Note whether the condition is intermittent, temperature-dependent or persistent and whether it starts at the edge or centre. Do not call every visual obstruction ‘fogging failure’ before locating it.

Cavity-condition record
FieldRecord
Unit/opening identity[enter]
Surface locationExterior / room side / cavity / uncertain
Appearance/patternHaze, droplets, deposit; edge/centre
TimingFirst observed; intermittent/persistent
ConditionsTemperature, sun, humidity and cleaning
Comparable unitsBatch, elevation and configuration
Evidence retainedImages, label and samples if applicable

4. Review manufacturing and component controls

Request records appropriate to the contract and issue: incoming component identity, glass washing, spacer/desiccant preparation, sealant proportioning and application, corner continuity, gas-fill control, curing/handling, quality checks and non-conformance closure. Do not demand confidential recipes; require objective traceability and the agreed evidence.

FGIA’s certification description emphasises continued materials/methods and quality-system surveillance. A later spacer, sealant, desiccant or coating substitution should be assessed against certification and compatibility requirements before production.

  • Approved bill of IGU materials
  • Component lot and expiry/storage controls
  • Equipment and process checks
  • Seal geometry/continuity observations
  • Gas-fill verification route where specified
  • Finished-unit identification
  • Non-conformance and rework record
  • Change authorisation and certification impact

5. Separate factory durability from glazing exposure

Edge seals can be affected by unsupported edges, standing water, blocked drainage, incompatible glazing materials, ultraviolet exposure outside the intended design, excessive movement or edge damage. Review the frame drainage, setting blocks, bite, sealant/gasket compatibility and installation condition.

A field concern may involve manufacture, glazing, transport, building movement or several interacting factors. Keep the product-family test evidence and installed-condition evidence in separate columns until the responsible review connects them.

Factory-versus-field evidence
Evidence streamExamples
Factory configurationComponents, process, certification and batch
Transport/storageRacking, edge protection and exposure
Glazing systemBlocks, bite, drainage and compatibility
Building conditionsMovement, heat, moisture and UV exposure
Service historyCleaning, damage, repairs and timing

6. Build an auditable claim package

Connect the opening mark, IGU permanent marking, whole-unit and detail images, dates, configuration, delivery, installation and maintenance records. Notify through the contract/warranty route without waiting for a speculative cause conclusion.

If replacement is authorised, record whether the original make-up remains available and revalidate coating, spacer, colour and certification. Preserve removed evidence where an investigation requires it.

IGU issue dossier
ControlRecord
Issue and locationID, opening and pane
Unit identityMarking, fabricator and date code
Condition evidenceViews, surface check and timeline
ConfigurationApproved and actual make-up
Factory/field recordsBatch, delivery and glazing
DispositionInspection, cause status and remedy authority
Replacement verificationNew identity and configuration

7. Prevent repeat issues through project release controls

Before mass production, approve the complete IGU bill, representative sample, certification applicability, maximum sizes, edge/support route, component compatibility and quality-plan hold points. Tie every change to renewed review.

At delivery, reconcile permanent markings and opening labels. At installation, protect edges and drainage. At handover, retain the glass schedule and replacement description so future procurement does not reverse-engineer the unit from appearance.

Worked example: three photographs are not three diagnoses

Imagine a buyer receives three photographs from different rooms: one just after a shower, one on a cold morning and one showing a patch that remains later in the day. These hypothetical observations do not prove a shared defect. A useful first return identifies the opening, time, room use and which accessible surface appears affected. If the surface cannot be identified safely, write unknown.

Ask for a repeat overview from the same indoor position and record whether the appearance changes as conditions change. Retain the original images. Do not combine different openings into a single before-and-after sequence. Where an accessible surface can be checked under approved cleaning instructions, record that observation separately; do not remove glazing beads or reach outside to identify a cavity.

Send the observations to the responsible glazing or service team with the unit identification and original glass schedule. Ask them to distinguish an observed symptom from a confirmed cause and identify any further inspection. Surface moisture, an inaccessible mark and an uncertain photograph require different follow-up; a buyer should not decide that all three need a new sealed unit from the pictures alone.

Prepare a replacement enquiry without losing the investigation

If replacement is proposed, keep two linked records: the technical disposition of the reported unit and the specification of the proposed replacement. A quotation can be requested while the cause remains unresolved, but it should not silently turn that uncertainty into a confirmed warranty claim.

Return the opening mark, original order reference, available unit markings, approved glass build-up and required appearance. Ask the supplier which dimensions and interfaces must be verified by a competent installer before manufacture. If the original coating or glass product is unavailable, request the proposed substitution and an appearance review beside retained glazing rather than accepting a description such as equivalent glass.

Agree whether the removed unit must be retained for inspection, who will handle it and when disposal is authorised. Identify it before the opening reference is lost. Close the replacement record after the responsible team confirms installation and the agreed checks; retain any unresolved cause or commercial decision in the service record.

Compare the condensation diagnosis guide with the after-sales guide before sending a glass replacement enquiry with your opening reference.

FAQ

Does an IG certification label guarantee lifetime fog-free service?

No. It supports conformity to a defined program and listed assembly; it does not replace project warranty or field investigation.

Does haze always prove seal failure?

No. First locate the condition and distinguish exposed-surface contamination, coating/optical effects and cavity moisture or deposits.

Can one certified assembly cover every component substitution?

Do not assume so. Compare the listed product family and program change requirements.

Why do drainage and glazing materials matter?

Installed edge exposure, standing water, movement and incompatibility can affect the IGU environment.

Can gas loss be determined visually?

No. Gas concentration requires an appropriate measurement/evidence route.

Continue the project review

Connect this guide with the proposed window and door systems, then review how Cavorlen approaches manufacturing and quality control. When your schedule is ready, send it through the project review form.

Official sources used

FGIA — Insulating Glass Certification ↗FGIA — IGCC/IGMA and IGMAC Procedural Guide ↗FGIA — Fundamentals of Insulating Glass ↗

Related buyer guides

Editorial boundary

This guide does not certify an IGU, prove seal failure, determine gas concentration, assign warranty responsibility or predict service life.