A project decision is not controlled until the question, answer, authority, affected documents and current status can be retrieved without reading an entire chat history.

The drawing says inward opening, the translated schedule says outward, and a meeting message says “follow the latest”. Production asks which document is latest and receives three screenshots. Cross-border communication fails less often because people did not speak; it fails because the project cannot distinguish discussion from instruction.

Use boundary: This guide proposes a project-control method. The contract, information-security requirements and authorised project procedures govern the actual document hierarchy, approvals and confidentiality obligations.

1. Put technical questions in one RFI register

Give every question a unique ID, subject, affected opening marks/documents, originator, owner, due date, response, attachments and status. Separate proposed answers from approved instructions.

A screenshot can support context but should not be the only record of a geometry, configuration, price or programme decision. Link the approved response to revised drawings, schedules or variations where those documents must change.

Technical question register
FieldRecord
RFI ID and subject[enter]
Affected marks/documents/revisions[enter]
Question and proposed options[enter]
Decision owner and due date[enter]
Approved response and date[enter]
Documents/actions changed[enter]
Status and closure evidence[enter]

2. Turn meetings into a decision record

Issue minutes promptly with attendees, documents reviewed, decisions, open questions, owners and dates. Ask participants to correct misunderstandings within the agreed review period.

Do not use silence as approval unless the contract and procedure explicitly create that effect. Mark discussion items, recommendations and authorised decisions differently so production cannot mistake a conversation for release.

  • Meeting purpose and time zone
  • Attendees and authority roles
  • Documents and revisions reviewed
  • Decisions and exact scope
  • Open items and dependencies
  • Owner and due date
  • Required drawing/commercial updates
  • Minutes review and acceptance route

3. Name who may approve each controlled item

Create an authority matrix for drawings, window schedules, samples, colours, glass, hardware, substitutions, price changes and production release. A senior job title does not automatically provide authority for every subject.

When an approver changes, issue the change through the controlled contact route. Keep technical review, commercial acceptance and legal variation separate where the project requires different authorities.

Approval authority matrix
Controlled itemPreparer/reviewerAuthorised approverRelease evidence
Shop drawings/schedule[enter][enter]Approved revision
Sample/finish/glass[enter][enter]Approval record
Technical substitution[enter][enter]Disposition and evidence
Price/programme change[enter][enter]Contract variation
Mass-production release[enter][enter]Release record

4. Control bilingual documents and terminology

The contract should identify the prevailing language and the process for resolving inconsistencies. For working documents, keep source, translation, reviewer, version and date visible; do not overwrite the earlier language file without traceability.

Build a project glossary for sash, fixed light, mullion, transom, glazing bead, handing, sightline, frame size, rough opening, hardware and interfaces. Add sketches where orientation words remain ambiguous. A glossary reduces variation; it does not override a controlled drawing.

Bilingual terminology record
Term/conceptLanguage ALanguage BSketch/referenceApproved use
Opening direction[enter][enter]Viewpoint stated[enter]
Opening/frame size[enter][enter]Dimension basis[enter]
Frame members[enter][enter]Section reference[enter]
Hardware/interface[enter][enter]Schedule/detail[enter]

5. Design response times around decisions and time zones

Classify questions by consequence: safety or production stop, imminent procurement decision, normal technical review, and information only. Define acknowledgement and substantive-response targets, escalation and what work must pause while an answer remains open.

A twelve-hour time difference can turn one unclear message into a two-day loop. Send complete question packets before the overlap window: marked drawing, exact revision, proposed options, required decision and deadline.

  • Urgency and consequence
  • Time zones and overlap window
  • Acknowledgement vs final-answer target
  • Information required for review
  • Named escalation path
  • Work allowed or held pending answer
  • Next-update commitment

6. Put holidays and supply interruptions in the baseline

Record Chinese public holidays, factory shutdown, maintenance and key supplier closures alongside destination holidays, shipping cut-offs and site dates. Confirm the factory’s actual plan; a national holiday date does not reveal its material cut-off or restart ramp-up.

Freeze drawings, colours and long-lead materials before the relevant cut-off, or show the uncertainty in the programme. Do not promise a shipment date that assumes immediate full output after a closure.

Programme question: Which approval or material decision must be complete before the next real cut-off, and what happens to shipment if it is late?

7. Remove unnecessary sensitive information before sharing drawings

Classify drawings and documents before external distribution. Share only the pages and fields needed for quotation, engineering or production; remove unrelated client details, security layouts, personal data and commercially sensitive layers where authorised.

Use named recipients, approved storage, access expiry, download controls where available and a distribution record. Redaction must not remove information needed to make the technical decision safely. When in doubt, ask the project information owner rather than improvising.

  • Document owner and classification
  • Purpose and minimum necessary content
  • Authorised recipients
  • Redaction and technical completeness check
  • Approved channel and access period
  • Confidentiality obligation
  • Distribution and withdrawal record

8. Publish one current project baseline

Maintain a current register of contract documents, drawings, schedules, samples, RFIs, variations and production releases. Each entry needs a revision, status and effective date. Superseded files remain traceable but must not appear current.

ISO 10013 provides guidance for documented information tailored to an organisation’s needs. The practical outcome here is not more paperwork; it is a reliable answer to what the team should use today.

Current project baseline
Record typeCurrent identifier/revisionStatus/effective dateOwner/location
Contract/scope[enter][enter][enter]
Drawings/schedule[enter][enter][enter]
Samples/configuration[enter][enter][enter]
RFI/decision register[enter][enter][enter]
Variations[enter][enter][enter]
Production release[enter][enter][enter]

Resolve a left-right disagreement without guessing the viewpoint

In a hypothetical enquiry, an English schedule says left opening, a translated message says right opening, and a photograph is taken from outside. Do not settle the conflict by choosing the latest chat timestamp. Ask for a sketch that states the viewing side, identifies fixed and moving panels, and shows the intended movement for the affected opening mark.

Attach the conflicting schedule and drawing revisions to one question. Ask the authorised reviewer to confirm the intended arrangement on the sketch and identify which controlled documents must change. For a sliding unit, show the panel arrangement and travel; for a hinged unit, show the relevant hinge side and swing. The sketch clarifies the question but is not a release until the required approval is recorded.

After the decision, check the translated schedule against the revised drawing rather than translating the short left-right message again. Record which language version was reviewed and by whom. Do not infer that the same correction applies to mirrored rooms or other opening marks unless the decision explicitly includes them.

Make the response actionable across a time-zone gap

Use a compact decision packet: affected marks; current revision; conflicting instruction; viewpoint-labelled sketch; decision requested; consequence of delay; named decision owner; and deadline with date and time zone. Separate acknowledgement of receipt from the actual decision. A message that says received must not appear as approved in the production register.

If the answer is pending at the next working-day handover, state the affected work that remains on hold and any unrelated work permitted by the authorised project process. Do not create a blanket factory shutdown or a silent production release from an unresolved wording question.

When the answer arrives, link it to the revised schedule, drawing and release reference, and notify the parties using the superseded copy. Keep the old version traceable but clearly withdrawn from current use. This makes the decision recoverable without searching personal messaging histories.

Use the window specification checklist together with the sample-approval guide for the related steps. Discuss your project documents with the project reference and relevant opening marks.

FAQ

Can WhatsApp or WeChat be used for project communication?

They can support communication, but controlled decisions should be transferred into the agreed project record with authority and affected documents.

Which language should prevail?

The contract and qualified legal advice determine that. State the rule explicitly rather than assuming English always governs.

Does no reply mean a drawing is approved?

Only if the contract and procedure clearly establish that effect. Otherwise obtain the required authorised disposition.

How detailed should an RFI be?

Enough to identify the exact issue, affected documents and marks, decision needed, options and consequence of delay.

Should every drawing be shared with every supplier?

No. Share the minimum authorised information needed while preserving technical completeness and required confidentiality controls.

Continue the project review

Connect this guide with the proposed window and door systems, then review how Cavorlen approaches manufacturing and quality control. When your schedule is ready, send it through the project review form.

Official sources used

ISO 10013 — Guidance for documented information ↗ISO — Release of ISO 10013:2021 ↗ISO — Guidance on documented information for ISO 9001:2015 ↗

Related buyer guides

Editorial boundary

This guide does not create contractual authority, determine the legally prevailing language, or replace the project document-control and information-security requirements.